Issue Sheet
File Number: Z25-010
Agenda Date: 10/06/2025
In Control: Mayor and CouncilFile Type: Zoning Item
Agenda Section:
Formal Business
Department: Community Development
Agenda Title:
Public Hearing – Zoning Amendment – Z25-010 – Allow revisions to the currently approved site plan 
and elevations for a 3,605 sq. ft. bank – Land Lot 559 – 0.65 acres – LGE Community Credit Union – 0 
& 2934 Atlanta Road
Ward 3 Councilmember - Travis Lindley
ISSUE AND BACKGROUND:
LGE Community Credit Union is requesting a zoning amendment of Z22-014 for 2934 & 0 Atlanta Road 
to amend the site plan, elevations, and zoning conditions for the development of a 3,605 sq. ft., 
credit union with 25 surface level parking spaces.
Being within the Urban Design District approval is required by the Urban Design Commission. On 
September 19, 2025, the Urban Design Commission voted to approve the application. 
RECOMMENDATION / REQUESTED ACTION:
Community Development recommends approval of the zoning amendment to amend the site plan, 
elevations, and zoning conditions on 0.65 acres for a one-story, 3,605 sq. ft. credit union, including the 
variance supported by staff as shown above, with the following conditions:
Standard Conditions
Requirements # 2, 3, 4, 8, 16 and 17 from Section 1201 of the Zoning Code are not applicable. The 
following requirements remain applicable.
1. The composition of the mixed-use building shall include a mixture of elements including; but not 
limited to: brick, stone, shake, hardy plank and stucco. No elevation shall be comprised of 100 percent 
hardy plank siding. The residences along external roadways shall not be permitted to utilize hardy 
plank for any elevation facing these roads.
2. The retention pond shall be placed and screened appropriately to be unobtrusive inside and 
outside the development. The storm water detention plan shall be designed to create at least a ten 
percent reduction in a 100-year storm event. The city engineer shall approve all plans.
3. All utilities within the development shall be underground.
4. The developer shall be responsible for any traffic improvements (including additional right-of-way 
dedications) deemed necessary by either the City or the County during construction plan review.