Committee of the Whole - HR Training Room — Minutes

Open official source ↗ · Source page 6

SHA-256 35b0b2bd6099e807e8d4da255181cc62af58a6abb168383c1fa667ad7a136319 · Captured source extract

6:00 PM 
 
City of Smyrna 
Mayor and Council Meeting 
2800 King Street SE 
Human Resources Training Room 
 
Page 6 of 9 
 
  
- Schedule: November 2023 – April 2028  
• Concept Phase: Nov 2023 – July 2026 
• Environmental Activities | Preliminary Plans Phase: Dec 2023 – July 2026 
• Preliminary Plans Phase | Preliminary Field Plan Review: Dec 2024 – Sep 2026 
• Right-of-way Plan Activities: July 2026 – Oct 2026 
• Final Design & Right-of-Way Acquisition | Final Field Plan Review: Aug 2026 – Oct 
2027 
• Prepare for Let | Let Contract: Aug 2027 – April 2028 
 
Tolleson Park Aquatics Center 
Under Construction – Estimated Completion April 2027 
Awarded to Reeves + Young 
- Schedule: August 2024 – April 2027  
• Concept Development: Aug 2024 – Jan 2025 
• Schematic Design: April 2025 – June 2025 
• Design Development: Just 2025 – Aug 2025 
• Construction Documents: Aug 2025 – Oct 2025 
• Advertising/Bidding Award: Sept 2025 – Nov 2025 
• Construction: Dec 2025 – April 2027 
 
River Line Park Splashpad/Playground 
Grand Opening May 1, 2026 
  
Downtown Parking (Surface Lot) 
Substantially Complete 
  
Resurfacing 
Proposed Roads  
• Ventura Road 
• Ventura Place 
• Reed Street SE 
• Linwood Drive SE 
• Alpine Drive 
• Manson Avenue 
• Highview Drive Cloudland Drive 
• Davenport Street 
• Knoll Road 
• Quarles Avenue 
• Wills Street 
• Stephens Street 
• Cobb Lane 
• Village Walk 
• Back Parking Lot / City Hall 
• Hamby Street 
• Powder Springs Street 
• Pine Hill Drive 
• Whitefield Court 
• Pat Mell Road 
• Old Concord Road 
• Vineyard Court 
• Chateau Way 
• Rose Court