2025-04-24 April 24, 2025 Mayor and Council Work Session_Retreat Meeting Minutes - DRAFT

Open official source ↗ · Source page 2

SHA-256 59abb06dbd0528cfb0acd6e8ce7070901fce9f51ab3d31cb5f9cb9e1765cf511 · Captured source extract

 
January 09, 2025 
12:00 PM 
 
City of Smyrna 
Mayor and Council Meeting 
Lanier Islands  
Legacy Lodge & Conference Center 
7000 Lanie Islands Pkwy 
 
Page 2 of 5 
 
• Grade separation between Windy Hill and S. Cobb Dr. – county and state project 
 
Tolleson Pool/Tennis: 
 
• Combination of 2022 SPLOST, need additional $8M to fully fund with bond 
• Focal point for Councilmember Lindley – complete by Memorial Day 2027 
• Questions about Croy’s timeline – approved timeline was six weeks ago 
• Moving pipe that is six feet in the ground, and concrete crusher was in the shop 
• This needs to be moved to an outside contractor and of city hands 
• A Project Manager should be leading this – move everything under Croy 
• Councilmember Welch said Croy was supposed to present final plans, but no final plans 
came forward 
• Councilmember Lindley said Croy needs to provide regular updates 
• Councilmember Lindley said timeline is concerning 
• Councilmember Lindley mentioned communications are in a bad state; stated it takes 
nine clicks to find any information about this project on the website; city hired 
communications consultant that does little for the city; wants a better communications 
plan to highlight successes throughout the city 
• Councilmember Hines wants a communications update; most people do not go to social 
media to research updates about the city; social media should complement the website, 
not replace it 
• Consensus is that council is underwhelmed with communication/public relations; there is 
no communications plan 
 
Ward 7 Splash Pad: 
 
• Combination of 2022 SPLOST and General Fund 
• Finished at the end of 2025 
• There was a small change order 
• Croy is managing the project / project administration 
 
First Baptist Church Development: 
 
• Church will rent from the city until their new church is completed  
• Councilmember Welch asked about the process going forward after citizen input. Andrea 
Worthy will be providing an update tomorrow 
• The property is 9 acres plus another ½ acre from neighboring property 
• There is a requirement by the bonding agency that the city has to have a certain 
percentage of expenses in general fund = $17.5M 
 
First Baptist Chapel Renovation: 
 
• $500K in bond, sold the Atlanta Rd property ($3.3M) – part of this bought the GA Power 
building, part of it is sitting in a bond disposition account 
• December 2027 – the new church building may be substantially complete 
• Timeline to spend the $1.7M – by end of December 2026 
• Mayor Pro Tem Gould asked about ADA compliance. It will need to be brought up to code 
 
Georgia Power Building: 
 
• $1.5M for renovations to be completed by April 2026 
• Awaiting a structural engineer’s review