Page 4 of 5 
 
• Prepare for Let | Let Contract: Aug 2027 – April 2028 
 
Tolleson Park Aquatics Center – Under Construction, Estimated Completion March 2027 
- Schedule: August 2024 – March 2027  
• Concept Development: Aug 2024 – Jan 2025 
• Schematic Design: April 2025 – June 2025 
• Design Development: June 2025 – Aug 2025 
• Construction Documents: Aug 2025 – Oct 2025 
• Advertising/Bidding/Award: Sep 2025 – Nov 2025 
• Construction: Dec 2025 – March 2027 
 
Riverline Park Splashpad/Playground: Completion January 2026 
Downtown Parking (Surface Lot): Substantially Complete 
Resurfacing: 31 Proposed Roads 
Downtown Improvements: Construction Complete 
  
Upcoming Projects: December 2025  
• Cobb Parkway Pedestrian Bridge: Project in Concept Development (PDP) 
• Camp Highland – Slope Stabilization: Silver Comet Trail Reopened 
 
Brief discussion about joint projects with Cobb County.  
 
5. Review of Current M&C Agenda 
 
 A. COW2025-119 Review of the December 15, 2025 Mayor and Council Meeting Notice and 
Agenda  
 
 
Mayor Derek Norton reviewed the December 15, 2025 Mayor and Council meeting 
agenda. 
  
ATH2025-198: Paul Osburn, Deputy Public Works Director, explained that the retractable 
bollards will be at Bank St. and King St., Powder Springs St. and King St. by the brewery 
and the parallel parking where the food trucks are supposed to be. They will also be 
installed at Village Green at Atlanta Rd. They are quick release, so they should go up and 
down within 30 seconds. Reflectivity will be installed, and they will be installed by internal 
staff with oversight by an appropriate manufacturer representative which will save the City 
a quarter of a million dollars. 
  
RFP26-011: This allows the City to have an on-call set of contractors to utilize. 
  
ATH2025-210: This allows one contractor to manage the whole project from design to 
installation. This will be an upgrade from what was there before. It will tie into the river 
keepers building. It will be ADA compliant, elevated, tied into the trail, etc.  
  
ATH2025-211: This just increases the budget line item to do additional outfall clearing. 
 
6. Other Business / Staff Comment 
 
Paul Osburn, Deputy Public Works Director, discussed the bagged leaf issues. Staff has 
attempted multiple ways to handle the bagged leaf issues from residents. Door hangers were 
distributed with the new rules. Ten bags or fewer are free. Communication will be better before 
the next fall season.