Smyrna River Line Splash Pad CEI Proposal
Open official source ↗ · Source page 3
200 Cobb Parkway North | Building 400, Suite 413 | Marietta, Georgia 30062 |770.971.5407
croyengineering.com
the construction work by a Field Representative. Pl ease note that material testing and geotechnical
services costs are not included in this fee proposal.
• Conduct site visits (part-time) to provide observa tion and inspection of the construction to
ensure work is generally being completed in accorda nce with the Contract Documents
(average of 10 hours per week)
• Prepare site visit observation reports for each vi sit recording activity at the site and progress
of the work with photos
• Field verify quantities and review monthly contrac tor pay applications
• Assist the City with coordination of the geotechni cal consultant for scheduling of material
testing services
• Review material testing reports (by others) and co ordinate any deficiencies with the Contractor
Task Budget: 42,900.00
Total Project Budget: $131,900.00
III. ADDITIONAL SERVICES
Services that are not included but may be provided by Croy as an additional service include:
• Surveying services
• Landscape architect/arborist services
• Tree protection plan or tree recompense
• Architectural services
• Structural engineering
• Stormwater management design/hydrology study
• Utility company coordination
• Offsite infrastructure improvement designs and per mitting
• Bid phase services
• Written technical specifications
• Public meeting attendance
• Environmental services
• Construction cost estimating
• As-built/record drawing services
IV. DELIVERABLES
• Site Visit Reports (during OAC meeting site visit)
V. APPROVAL FORM
APPROVED: City of Smyrna
Department Head
Signed Signed
Joe Bennett, City Administrator
Name
Attest
Heather K. Peacon-Corn, City Clerk Title