License and Variance Board Meeting - Council Chambers — Minutes

Open official source ↗ · Source page 3

SHA-256 7421621240b918df7e08740588cc14ba1338dcf7c714c9329ce38c67166ccb6c · Captured source extract

 
June 24, 2026 
10:00 AM 
 
City of Smyrna 
License and Variance Board Meeting 
2800 King Street SE 
Council Chambers 
 
Page 3 of 18 
 
along the western side of Elizabeth Street: 2870 Elizabeth Street (V14-040-042), 2890 
Elizabeth Street (V13-011 and V20-055), and 2910 Elizabeth Street (V06-020). 
Community Development has not received any calls in opposition to the requests. 
  
The applicant is requesting to deviate from the City’s R-15 Zoning District and 
substandard lot requirements. According to Section 1403 of the Zoning Ordinance, 
variances must be reviewed under the following standards: (1) Whether there are unique 
and special or extraordinary circumstances applying to the property; (2) Whether any 
alleged hardship is self-created by any person having an interest in the property; (3) 
Whether strict application of the relevant provisions of the code would deprive the 
applicant of reasonable use of the property; and (4) Whether the variance proposed is the 
minimum variance needed. Community Development has reviewed the request and 
believes that the variances will not adversely affect surrounding residents since a house 
previously occupied the property. Therefore, staff recommends approval of the requested 
variances with the following conditions:  
 
1. Approval of the requested variances shall be conditioned upon substantial 
compliance with the site plan and elevations submitted with the variance 
application. 
2. An as-built survey shall be submitted prior to foundation pour due to the proximity 
to the setbacks. 
3. A Stormwater Inspection and Maintenance Agreement shall be completed and 
recorded with the Cobb County Superior Court prior to issuance of the building 
permit. 
4. A stormwater as-built certification statement shall be submitted to Community 
Development for approval prior to issuance of the Certificate of Occupancy. 
5. The existing 12-inch Reinforced Concrete Pipe (RCP) must be replaced with 18-
inch RCP prior to issuance of the Certificate of Occupancy. 
6. A drainage easement must be provided and completed prior to building permit 
issuance. Once the easement is signed, it must be recorded with the Cobb County 
Superior Court. 
 
Sandy Steichen (400 Belmont Place), applicant/owner, stated she understands and 
agrees to the six stipulations read into record.  
  
Mark Wolff, City Engineer, stated this has been reviewed by Engineering. Mitigation 
requires an inspection maintenance agreement. 
  
A public hearing was called, and no one came forward in favor of or in opposition to this 
item. The public hearing was closed.  
 
Board Member Andrea Worthy made a motion to approve V26-049; seconded by Board 
Member Dustin Davey. 
 
The motion to approve carried with the following vote: 
 
Aye: 3 –  Chairperson Garland, Board Member Worthy, Board Member Davey 
Nay: 0 –  None 
Recuse: 0 –  None 
 
 B. V26-050 Public Hearing - Variance Request - V26-050 - Increase the maximum impervious 
surface area from 35% to 36.1% - Land Lot 559 - 2880 Elizabeth Street - Sandy Steichen 
Ward 3 Councilmember - Travis Lindley