the project scope and study. The attached draft is developed from the template provided 
by the USACE. 
  
The USACE has not yet scoped the project and so the actual costs have not yet been 
determined. The letter constitutes an expression of interest and is not a contractual 
obligation. 
 
4. Review of Current M&C Agenda 
 
 A. COW2025-027 Review of the February 17, 2025 Mayor and Council Meeting Notice and 
Agenda  
 
Mayor Norton reviewed the February 17, 2025 agenda. 
  
ATH2025-033: Eric Randall, Public Works Director, provided the following background: 
  
Following the approval of the Intergovernmental agreement to share costs associated with 
the Camp Highland Bridge bank stabilization, Cobb County solicited bids to perform the 
work.  The lowest reliable bid received exceeded the estimated construction costs, and 
Cobb County and the Contractor agreed on a scope reduction that resulted in a revised 
construction cost of $3,145,107.77. In keeping with the intent of sharing the costs for the 
project, the City and the County amount will be $1,572,553.88.  
  
The Intergovernmental Agreement also stipulates that the cost for engineering and design 
services related to the project in the amount of $41,730.00 would be cost shared 50/50 
between Cobb County and the City.  
  
To meet this, an additional $94,200.00 needs to be added to the allocation for the project 
in the 2022 SPLOST, for a rounded total budget of $1,594,200.00. 
  
Councilmember Oglesby asked if there is a plan for a sidewalk. Mr. Randall stated 
sidewalks are not part of this plan. This project was considered in 2016 and added to the 
2022 SPLOST. During bridge inspection, it was determined it is not the city’s. Georgia 
DOT determined it is Cobb County’s responsibility even though it primarily serves 
residents of the city. This may end up being a culvert rather than a bridge during the 
process if it is found to be more cost effective. This will not close the bridge, but it may 
close the trail. This is just for stabilization. 
  
There was no further discussion. 
 
5. Other Business / Staff Comment 
 
6. Executive Session (As Needed) 
 
Councilmember Travis Lindley made a motion Enter into Executive Session at 8:21 PM to 
discuss LEGAL; seconded by Councilmember Glenn Pickens. 
 
The motion Enter into Executive Session carried with the following vote: 
 
Aye: 7 –  Councilmember Pickens, Councilmember Hines, Councilmember Lindley, 
Councilmember Welch, Councilmember Wilkinson, Mayor Pro Tem / 
Councilmember Gould, Councilmember Oglesby