GovernSmyrna.

Issue Sheet

Open official source ↗ · Source page 1

SHA-256 861787d38c3ee46810b7ff7fdb2059279cddd7eab5ac755dddcf99fb9d1c411a · Captured source extract

City of Smyrna
Issue Sheet
File Number: ATH2025-040
A Max Bacon
City Hall
2800 King Street
Smyrna, GA 30080 
Agenda Date: 3/3/2025
In Control: City Council File Type: Authorization
Agenda Section:
Consent Agenda
Department: Public Works
Agenda Title:
Authorization to approve an extension of the current road closure at 560 Powder Springs Street until 
March 14, 2025.
Ward 5 Councilmember - Susan Wilkinson
ISSUE AND BACKGROUND:
This request is based off the findings that the city’s 60-inch corrugated metal storm drainpipe has 
failed and is causing the roadway to fail. The city is replacing the existing corrugated metal pipe with a 
new concrete box culvert. The anticipated length of construction is approximately 35 days. This 
occurred due to utility conflicts as well as minor unforeseen scope changes due to additional failed 
storm drainpipe that was determined unsafe and needed replacement.
 
RECOMMENDATION / REQUESTED ACTION:
Public Works recommends approval an extension of the current road closure at 560 Powder Springs 
Street until March 14, 2025.