Issue Sheet
File Number: ATH2026-083
A Max Bacon
City Hall
2800 King Street
Smyrna, GA 30080 
Agenda Date: 6/15/2026
In Control: City Council File Type: Authorization
Agenda Section:
Formal Business
Department: Public Works
Agenda Title:
Authorization to approve WK Dickson & CO., LLC, an Ardurra Company (1350 Church Street Ext NW 
#200, Marietta, GA 30060) to begin Phase I (Task Order #6) of a citywide multiyear multiphase 
Stormwater Watershed Masterplan Project in an amount not to exceed $201,100.00 to be funded 
from the FY26 Operating Budget Engineering Professional Services line item and authorize the Mayor 
to sign and execute all documents. 
Citywide
ISSUE AND BACKGROUND:
This request is based on the critical need for the development of a comprehensive citywide 
Stormwater Master Plan. The effort will include multiple sub-watershed evaluations identified by the 
City of Smyrna and its engineering consultants as necessary components of the overall master 
planning process. The completion of these sub-watershed studies will provide the data, analysis, and 
recommendations needed to develop a comprehensive understanding of the City's stormwater 
infrastructure, drainage systems, and flood-prone areas. The resulting Stormwater Master Plan will 
serve as a strategic tool for prioritizing capital improvements, identifying infrastructure deficiencies, 
and establishing a long-term framework for stormwater management. By developing this plan, the 
City will be better equipped to effectively plan, budget, and implement projects necessary to address 
nuisance flooding, improve drainage performance, enhance public safety, and increase the resilience 
of the community to future stormwater impacts.
 
RECOMMENDATION / REQUESTED ACTION:
Public Works and Engineering recommend approval of the proposed request.