June 15, 2026 
7:00 PM 
 
City of Smyrna 
Mayor and Council Meeting 
2800 King Street SE 
Council Chambers 
 
   Page 6 of 11 
Aye: 6 –  Councilmember Pickens, Councilmember Hines, Councilmember 
Welch, Councilmember Wilkinson, Mayor Pro Tem / Councilmember 
Gould, Councilmember Oglesby  
Nay: 0 –  None 
Absent: 1 –  Councilmember Lindley  
 
 D. ATH2026-081 Authorization to approve the City of Smyrna acquiring eighty-four (84) 
square feet of land or a 12’ x 7’ Water Easement from Campbell High School located 
at 2620 Ward Street in order for the City of Smyrna to be able to access and maintain 
its water meter and infrastructure that is located off the right-of-way and authorize the 
Mayor to sign and execute all documents. 
Ward 3 Councilmember - Travis Lindley 
 
Mike Jones, City Administrator, proved the following background: 
  
This request is necessary due to the existing infrastructure on the property that never 
had proper easements granted during the installation of the infrastructure. This will 
allow the City of Smyrna to be able to access and maintain its water meter and 
necessary infrastructure that is located off the right-of-way.  
 
Councilmember Glenn Pickens made a motion to approve item ATH2026-081; 
seconded by Councilmember Charles Welch. 
 
The motion to approve carried with the following vote: 
 
Aye: 6 –  Councilmember Pickens, Councilmember Hines, Councilmember 
Welch, Councilmember Wilkinson, Mayor Pro Tem / Councilmember 
Gould, Councilmember Oglesby  
Nay: 0 –  None 
Absent: 1 –  Councilmember Lindley  
 
 E. ATH2026-083 Authorization to approve WK Dickson & CO., LLC, an Ardurra 
Company (1350 Church Street Ext NW #200, Marietta, GA 30060) to begin Phase I 
(Task Order #6) of a citywide multiyear multiphase Stormwater Watershed Masterplan 
Project in an amount not to exceed $201,100.00 to be funded from the FY26 
Operating Budget Engineering Professional Services line item and authorize the 
Mayor to sign and execute all documents. 
Citywide 
 
Mike Jones, City Administrator, provided the following background: 
  
This request is based on the critical need for the development of a comprehensive 
citywide Stormwater Master Plan. The effort will include multiple sub-watershed 
evaluations identified by the City of Smyrna and its engineering consultants as 
necessary components of the overall master planning process. The completion of 
these sub-watershed studies will provide the data, analysis, and recommendations 
needed to develop a comprehensive understanding of the City's stormwater 
infrastructure, drainage systems, and flood-prone areas. The resulting Stormwater 
Master Plan will serve as a strategic tool for prioritizing capital improvements, 
identifying infrastructure deficiencies, and establishing a long-term framework for 
stormwater management. By developing this plan, the City will be better equipped to 
effectively plan, budget, and implement projects necessary to address nuisance