Active Projects: 
Windy Hill Road Improvements  
• Substantially Complete 
• Punch List of items to still be completed 
• Local Lanes are 25 MPH, Express Lanes are 45 MPH 
 
South Cobb Drive Improvements 
Funding Information 
  
• Concept Phase: Nov 2023 – July 2026 
• Environmental Activities | Preliminary Plans Phase: Dec 2023 – July 2026 
• Preliminary Plans Phase | Preliminary Field Plan Review: Dec 2024 – Sep 2026 
• Right-of-Way Plan Activities: July 2026 – Oct 2026 
• Final Design & Right-of-Way Acquisition | Final Field Plan Review: Aug 2026 – Oct 
2027 
• Prepare for Let | Let Contract: Aug 2027 – Apr 2028 
 
Tolleson Park Aquatics Center 
Pad-Ready Stabilization is Underway  
• Concept Development: Aug 2024 – Jan 2025 
• Schematic Design: Apr 2025 – Jun 2025 
• Design Development: Jun 2025 – Aug 2025 
• Construction Documents: Aug 2025 – Oct 2025 
• Advertising/Bidding/Award: Sep 2025 – Nov 2025 
• Construction: Dec 2025 – Mar 2027 
 
River Line Park Splashpad/Playground  
• Completion by end of 2025 
 
Downtown Parking (Surface Lot)  
• Substantially Complete 
 
Resurfacing  
• Church Street Remaining 
 
Downtown Improvements  
• Restroom/Playground Construction Underway – Open September 17 
 
Upcoming Projects: 
Cobb Parkway Pedestrian Bridge  
• Project in Concept Development (PDP) 
 
Camp Highland – Slope Stabilization  
• Silver Comet Trail Reopened 
 
Joint Projects with Cobb County: 
East-West Connector Roadway Safety Improvements  
• Turn Lane Extensions at Fontaine & Cooper Lake Roads 
 
Conversion of Sports Lighting to LED on Sports Fields/Courts  
• Chuck Camp and Tolleson are the only ones left to be converted