25122--Tolleson-Park-Aquatics-Center-002-PCCO-#002-July-2026_CroySigned

Open official source ↗ · Source page 1

SHA-256 c31c4bee4f5ca172e0868b403f9bd2686b51a3f87b36bd2bec0f2ad0838008cc · Captured source extract

Reeves Young
45 Peachtree Industrial Blvd
Sugar Hill, Georgia 30518
Phone: (770) 271-1159 
Project: 25122- - T olleson Park Aquatics Center
3530 King Springs Rd
Smyrna, Georgia 30080
Prime Contract Change Order #002: PCCO #002 - July 2026 ApprovedCost Items
TO: City of Smyrna
3180 Atlanta Road SE
Smyrna, Georgia 30080
FROM: Reeves Young, LLC
45 Peachtree Industrial Blvd., NW
Sugar Hill, Georgia 30518
DATE CREATED: 7/23/2026 CREATED BY: Matthew Graff (Reeves Young, LLC)
CONTRACT STATUS:Pending - Proceeding REVISION: 0
DESIGNATED REVIEWER:   REVIEWED BY:   
DUE DATE: 07/31/2026 REVIEW DATE:  
INVOICED DATE: 07/23/2026 PAID DATE:  
SCHEDULE IMPACT : EXECUTED: No 
  SIGNED CHANGE ORDER
RECEIVED DATE:
CONTRACT FOR: 25122-:T olleson Park Aquatics CenterTOTAL AMOUNT : $0.00
DESCRIPTION:
This Change Order herby amends a contract titled “Agreement for the Construction of the T olleson Park Aquatic Center” dated 12/5/2025 (the
“Agreement”), between City of Smyrna (“Owner”) and Reeves Young, LLC (“Contractor”), with respect to the above-referenced project. Capitalized
terms used but not defined in this Change Order will have the meanings given to those terms in the Agreement. The Agreement is hereby amended as
follows:
 
CE #006: Existing Footings 
CE #012: RFI #023: Pool Deck Sloping at Lap Pool 
CE #019: RFI #037: Column-Block Support 
CE #020: RFI #028: AED Clarification
CE #024: RFI #016: Cladding & Blocking at Storefront 
CE #034: RFI #039: Stone Veneer Clarifications
CE #050: T emporary Power for Restroom Building
CE #051: T emporary Power for Portable Restroom
 
This PCCO #002 hereby incorporates the above Change Events (CE's), associated Potential Change Orders (PCO's), corresponding Documents, all
pricing and time impacts. 
ATTACHMENTS:
 
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO # Title Schedule Impact Amount
010 #23: Pool deck sloping @ Lap Pool $0.00
013 #37: Column-Block support at exterior openings $0.00
015 CE #020 - #28: AED Clarification $0.00
017 Provia flatstone for receptacle installation $0.00
018 Existing Footers Encountered In New Excavation $0.00
019 #16 (Rev1): Curtainwall Attachment - Envelope Meeting $0.00
020 CE #050 and CE #051 $0.00
Total:  $0.00
 
CHANGE ORDER LINE ITEMS:
 
PCO # 010: #23: Pool deck sloping @ Lap Pool
# Budget Code Description Amount
1 03-1290-01-.SUB POOL DECK (2).SubcontractorDeck Drain $23,394.72
 
Reeves Young Page 1 of 3 Printed On: 7/28/2026  03:32 PM 
   
 
PCCO #002