25122--Tolleson-Park-Aquatics-Center-002-PCCO-#002-July-2026_CroySigned
Open official source ↗ · Source page 13
Reeves Young
45 Peachtree Industrial Blvd
Sugar Hill, Georgia 30518
P: (770) 271-1159
Project: 25122- - Tolleson Park Aquatics Center
3530 King Springs Rd
Smyrna, Georgia 30080
CHANGE EVENT #012 - RFI #023: Pool Deck Sloping at Lap Pool
Origin: RFI #23: Pool deck sloping @ Lap Pool
Date Created: 6/4/2026 Created By: Brent Newman
Status: Pending Scope: Out of Scope
Type: Owner Change Change Reason: Design Development
Description: The Contract Documents are hereby amended to include the additional Work resulting from the design changes and modifications contained within the RFI #023 response as
issued by CROY Engineering on 4/29/2026. The Work indicated by this RFI is outside of the current scope of the Work and constitutes a change. This CE is created for added
cost of trench drain, piping, and storm connection. CE originates from review of C-500, in which it was determined that sloping/elevations of pool deck at plan view north of slab
next to building would be deemed not acceptable per the Cobb County rules and regulations Part 8) section 1). This change is necessary in order to create positive drainage
away from pool edge. The RFI response consists of zero (0) new / revised drawings and includes the additional Work described below:
• ADD 100 FT of Specified Drain (per RFI #023 response)
• CREDIT Original Deck Drain
• 40' SDR26 PVC Piping
• Storm Connection
***NOTE: Previously presented as PCO #010.***
Contract Documents:
1. Amended to incorporate the Work modifications identified below.
The Work:
1. As described above.
Contract Time:
1. N/A
Contract Sum:
1. Per breakdown below.
Reeves Young, LLC reserves its' right to an equitable adjustment to the schedule and General Conditions required for the schedule impacts related to the scope of work
identified in this change order, but not known at this time until final commitments of fabrication and delivery are committed by Subcontractor(s). Should additional funds and time
be required to complete the project, Reeves Young reserves our right to increase our General Conditions, General Requirements, Fee, Overhead, Bond, and Insurance costs
for the additional funds required to complete the project. Reeves Young, LLC and W-SH HMR Owner IX, L.P . ("Owner") agree to work together with due diligence to determine
the adjustment due Reeves Young. By executing this Change Event, Ownership agrees that additional cost shall be Submitted by Reeves Young, LLC in a future Owner
Change Order and/or Invoice to Owner. Owner agrees to Pay Reeves Young, LLC the total amount of the Owner Change Order and/or Invoice which includes Reeves Young,
LLC's Fee and Insurance.
Reeves Young Page 1 of 2 Printed on: 7/10/2026 at 04:41PM EDT