Reeves Young
45 Peachtree Industrial Blvd
Sugar Hill, Georgia 30518
P: (770) 271-1159
Project: 25122- - Tolleson Park Aquatics Center
3530 King Springs Rd
Smyrna, Georgia 30080
CHANGE EVENT #020 - RFI #028: AED Clarification
Origin: RFI #28: AED Clarification
Date Created: 6/4/2026 Created By: Brent Newman
Status: Pending Scope: TBD
Type: Allowance Change Reason: Acceleration
Description: The Contract Documents are hereby amended to include the deductive change order resulting from the modifications contained within the RFI #028 response as issued by
CROY Engineering on 5/13/2026. This CE is created for deducting cost of AED & Training AED shown on G00.20 - Life Safety Plan. CE originates from information given to RY
by Pool Contractor that AEDs are not allowed in State of Georgia without a prescription. Per discussions at 4/30 OAC Meeting, City is to provide AED machines (City confirmed
Owner direct purchase). RFI #028 response requested credit for AEDs. The RFI response consists of zero (0) new / revised drawings and includes the additional Work
described below: 
 
***NOTE: Previously presented as PCO #015.***
Contract Documents:
1. Amended to incorporate the Work modifications identified below. 
 
The Work:
1. As described above.
   
Contract Time: 
1. N/A
 
Contract Sum: 
1. Per breakdown below. 
 
Reeves Young, LLC reserves its' right to an equitable adjustment to the schedule and General Conditions required for the schedule impacts related to the scope of work
identified in this change order, but not known at this time until final commitments of fabrication and delivery are committed by Subcontractor(s). Should additional funds and time
be required to complete the project, Reeves Young reserves our right to increase our General Conditions, General Requirements, Fee, Overhead, Bond, and Insurance costs
for the additional funds required to complete the project. Reeves Young, LLC and the City of Smyrna ("Owner") agree to work together with due diligence to determine the
adjustment due Reeves Young. By executing this Change Event, Ownership agrees that additional cost shall be Submitted by Reeves Young, LLC in a future Owner Change
Order and/or Invoice to Owner. Owner agrees to Pay Reeves Young, LLC the total amount of the Owner Change Order and/or Invoice which includes Reeves Young, LLC's Fee
and Insurance.