Change Order #002104-7 Date: June 30, 2026 Reeves Young Attn: Brent Newman bnewman@reevesyoung.com 45 Peachtree Industrial Blvd, Sugar Hill, GA 30518 Tolleson Park Aquatic Center 3530 King Springs Road, Smyrna, GA Contract: Contract Date: Changes DESCRIPTION COST ▪ Labor: Cutting and parging work at jambs of storefronts per RFI indicating these had to be cut back 3” on each side. o 1 mason, 40 hours $2,465.00 ▪ Materials: parging material for jambs. $216.40 ▪ Equipment: Scaffolding, saw, blades, etc. $1,250.00 OH&P $589.71 TOTAL CHANGE $4,521.11 *All terms and conditions of original proposal and subcontract still apply unless otherwise explicitly stated. Summary Original Contract Sum $749,250.00 Original Contract + previous CO’s $ Net Contract Change $4,521.11 New Contract Sum $ Respectfully Submitted by, Luis Pérez-Maldonado |Project Manager| Platinum Masonry, Inc. luis@platinummasonryinc.com |Mailings: 4370 Lawrenceville Highway, Lilburn, GA 30047 |o: (770) 896-4261|c: (943) 262-2594 |w: www.platinummasonryinc.com Contractor Approval (To be completed by an authorized contractor representative.) ****Please sign and return within 5 business days Signature: _______________________________________________ Name: Title: Date: $393.14 (10%) $4,324.54