# Budget Code Description Amount
2 31-0000- -.SUB EARTHWORK.Subcontractor Utilities $3,300.00
Subtotal: $26,694.72
CONTINGENCY FUNDS (-100.00% Applies to All Line Items ): $(26,694.72)
Grand Total: $0.00
 
PCO # 013: #37: Column-Block support at exterior openings
# Budget Code Description Amount
1 04-0000- -.SUB MASONRY .Subcontractor Masonry $2,726.09
2 05-1200- -.SUB FRAMING - STRUCTURAL
STEEL.Subcontractor Steel $6,370.00
Subtotal: $9,096.09
CONTINGENCY FUNDS (-100.00% Applies to All Line Items ): $(9,096.09)
Grand Total: $0.00
 
PCO # 015: CE #020 - #28: AED Clarification
# Budget Code Description Amount
1 13-1100- -.SUB LAP POOLS.Subcontractor POOL $(2,162.00)
2 99-4300- -.MTL CONTINGENCY .Material $2,162.00
Subtotal: $0.00
CONTINGENCY FUNDS (0.00% Applies to All Line Items ): $0.00
Grand Total: $0.00
 
PCO # 017: Provia flatstone for receptacle installation
# Budget Code Description Amount
1 04-0000- -.SUB MASONRY .Subcontractor Masonry $1,805.52
Subtotal: $1,805.52
CONTINGENCY FUNDS (-100.00% Applies to All Line Items ): $(1,805.52)
Grand Total: $0.00
 
PCO # 018: Existing Footers Encountered In New Excavation
# Budget Code Description Amount
1 13-1100- -.SUB LAP POOLS.Subcontractor Pool Excavation $1,050.00
2 01-6100- -.MTL DUMPSTERS.Material Dumpsters $500.00
Subtotal: $1,550.00
CONTINGENCY FUNDS (-100.00% Applies to All Line Items ): $(1,550.00)
Grand Total: $0.00
 
PCO # 019: #16 (Rev1): Curtainwall Attachment - Envelope Meeting
# Budget Code Description Amount
1 08-4000- -.SUB "ENTRANCES, STOREFRONTS,
AND CURTAIN WALLS".Subcontractor Metal Cladding $18,000.00
2 07-1000- -.SUB WATERPROOFING.SubcontractorCaulk $8,565.00
3 05-4000- -.SUB FRAMING - COLD-FORMED
METAL.Subcontractor Wood Blocking $21,685.00
4 04-0000- -.SUB MASONRY .Subcontractor Masonry - A/WRB $1,111.77
5 04-0000- -.SUB MASONRY .Subcontractor Masonry - CMU / Stone $4,324.54
Subtotal: $53,686.31
CONTINGENCY FUNDS (-100.00% Applies to All Line Items ): $(53,686.31)
Grand Total: $0.00
 
Reeves Young Page 2 of 3 Printed On: 7/28/2026  03:32 PM 
   
 