Project: 25122- Tolleson Park Aquatics Center
3530 King Springs Rd
Smyrna, Georgia 30080
 
 
RFI #37: Column-Block support at exterior openings
 
Revision 0 Status Closed on 05/13/26
To Luke T orbert (Croy Engineering) (Response
Required)
T om Robinson (Croy Engineering) 
From Alex Griffith (Reeves Young, LLC)
45 Peachtree Industrial Blvd., NW
Sugar Hill, Georgia 30518
Date Initiated May 9, 2026 Due Date May 14, 2026
Location Project Stage
Cost Impact TBD Schedule ImpactTBD
Spec Section Cost Code
Drawing Number Reference
Linked Drawings 
Received From  
Copies To Robert Crump (Southeastern Steel, Inc.), Semmes
Irby (Reeves Young, LLC), Luis Pérez-Maldonado
(Platinum Masonry, Inc.), Blaine Russell (Reeves
Young, LLC) 
 
 
Activity
 
Question Question from Alex Griffith Reeves Young, LLC on Saturday, May 9, 2026 at 11:39 AM EDT
  During our site walk on 5/8 with the EOR we discussed 4 exterior openings that show cmu block running to steel columns that
do not have support on the column side. 
Doors 119 & 119B
Pass through window at the south side concession area 
CW-7 at the north side 107 corridor 
 
It was discussed on site that the use of 2-4" lintels on both sides of the opening tied to the steel should be an acceptable
solution. 
 
Please advise 
  Attachments
Block-comlumn RFI.pdf, Block-column RFI2.pdf
 
Official ResponseResponse from Luke Torbert Croy Engineering on Wednesday, May 13, 2026 at 05:14 PM EDT
  Please see attached response from Shear
  Attachments
tolleson_park_aquatics_center-rfi#37-column-block_support_at_exterior_openings-202605132040_Shear.pdf
 
 