Change Order #002104-7 
Date: June 30, 2026 
Reeves Young 
Attn: Brent Newman 
bnewman@reevesyoung.com 
45 Peachtree Industrial Blvd, 
Sugar Hill, GA 30518 
Tolleson Park Aquatic Center 
3530 King Springs Road, 
Smyrna, GA 
Contract:  Contract Date:  
 
Changes 
DESCRIPTION COST 
▪ Labor: Cutting and parging work at jambs of storefronts per RFI indicating these had to be 
cut back 3” on each side. 
o 1 mason, 40 hours 
$2,465.00 
▪ Materials: parging material for jambs. $216.40 
▪ Equipment: Scaffolding, saw, blades, etc. $1,250.00 
OH&P $589.71   
 
TOTAL  CHANGE  
 
$4,521.11 
*All terms and conditions of original proposal and subcontract still apply unless otherwise explicitly stated.  
Summary 
Original Contract Sum $749,250.00 
Original Contract + previous CO’s  $ 
Net Contract Change $4,521.11 
New Contract Sum $ 
 
Respectfully Submitted by, 
Luis Pérez-Maldonado 
|Project Manager| Platinum Masonry, Inc.  
luis@platinummasonryinc.com |Mailings: 4370 Lawrenceville Highway, Lilburn, GA 30047 
|o: (770) 896-4261|c: (943) 262-2594 |w: www.platinummasonryinc.com 
 
Contractor Approval (To be completed by an authorized contractor representative.) 
****Please sign and return within 5 business days 
 
 
 
 
Signature: _______________________________________________    
Name: 
 
Title: 
Date: 
 
$393.14 (10%)
$4,324.54