Reeves Young
45 Peachtree Industrial Blvd
Sugar Hill, Georgia 30518
P: (770) 271-1159
Project: 25122- - Tolleson Park Aquatics Center
3530 King Springs Rd
Smyrna, Georgia 30080
CHANGE EVENT #034 - Provia Flatstone for Receptacle Installation
Origin: RFI #39: Stone Veneer Clarifications - Envelope Coordination Meeting
Date Created: 6/16/2026 Created By: Brent Newman
Status: Pending Scope: Out of Scope
Type: Owner Change Change Reason: Design Development
Description: The Contract Documents are hereby amended to include the additional Work resulting from the modifications contained within the RFI #039-1 response as issued by NELSON
Architecture, Inc. on 6/17/2026. The Work indicated by this RFI is outside of the current scope of the Work and constitutes a change. This CE is created for added cost of (52)
flat stone pieces at single gang receptacles. CE originates from 5/7 Envelope Coordination Meeting, in which Subcontractors gathered to discuss finish detail discrepancies for
the building(s). RY then presented discrepancies in the 5/13 Envelope Coordination Meeting (with CROY , NELSON, and RY), in which the use of Provia flatstone receptacle
pieces was confirmed. This change is necessary, as variance of stone thickness will create an undesired aesthetic without the use of these flat stone receptacle pieces. The RFI
response consists of zero (0) new / revised drawings and includes the additional Work described above.
 
***NOTE: Previously presented as PCO #017.***
 
Contract Documents:
1. Amended to incorporate the Work modifications identified below. 
 
The Work:
1. As described above.
   
Contract Time: 
1. N/A
 
Contract Sum: 
1. Per breakdown below. 
 
Reeves Young, LLC reserves its' right to an equitable adjustment to the schedule and General Conditions required for the schedule impacts related to the scope of work
identified in this change order, but not known at this time until final commitments of fabrication and delivery are committed by Subcontractor(s). Should additional funds and time
be required to complete the project, Reeves Young reserves our right to increase our General Conditions, General Requirements, Fee, Overhead, Bond, and Insurance costs
for the additional funds required to complete the project. Reeves Young, LLC and the City of Smyrna ("Owner") agree to work together with due diligence to determine the
adjustment due Reeves Young. By executing this Change Event, Ownership agrees that additional cost shall be Submitted by Reeves Young, LLC in a future Owner Change
Order and/or Invoice to Owner. Owner agrees to Pay Reeves Young, LLC the total amount of the Owner Change Order and/or Invoice which includes Reeves Young, LLC's Fee
and Insurance.
Attachments:
 
CHANGE EVENT LINE ITEMS
Reeves Young Page 1 of 2 Printed on: 7/17/2026 at 02:57PM EDT