25122--Tolleson-Park-Aquatics-Center-002-PCCO-#002-July-2026_CroySigned
Open official source ↗ · Source page 55
Reeves Young
45 Peachtree Industrial Blvd
Sugar Hill, Georgia 30518
P: (770) 271-1159
Project: 25122- - Tolleson Park Aquatics Center
3530 King Springs Rd
Smyrna, Georgia 30080
CHANGE EVENT #050 - Temporary Power for Restroom Building
Origin:
Date Created: 7/15/2026 Created By: Semmes Irby
Status: Open Scope: TBD
Type: Owner Change Change Reason: Cost of Work
Description: This Change Event #050 is created to capture costs of electrical work required to maintain new Restroom Building power from relocated site panel. This Work is outside of the
current scope of the Work and constitutes a change. CE is comprised of costs for time/labor, material, and equipment to maintain temporary power at Restroom Building as well
as all other components required for a complete installation. This work was done with the intent to open Restroom Building prior to power supply from Main Building Electrical
Room. This change was also necessary in order to ensure functionality of newly installed equipment.
Contract Documents:
1. Amended to incorporate the Work modifications identified above.
The Work:
1. As described above.
Contract Time:
1. N/A
Contract Sum:
1. Per breakdown below.
Reeves Young, LLC reserves its' right to an equitable adjustment to the schedule and General Conditions required for the schedule impacts related to the scope of work
identified in this change order, but not known at this time until final commitments of fabrication and delivery are committed by Subcontractor(s). Should additional funds and time
be required to complete the project, Reeves Young reserves our right to increase our General Conditions, General Requirements, Fee, Overhead, Bond, and Insurance costs
for the additional funds required to complete the project. Reeves Young, LLC and the City of Smyrna ("Owner") agree to work together with due diligence to determine the
adjustment due Reeves Young. By executing this Change Event, Ownership agrees that additional cost shall be Submitted by Reeves Young, LLC in a future Owner Change
Order and/or Invoice to Owner. Owner agrees to Pay Reeves Young, LLC the total amount of the Owner Change Order and/or Invoice which includes Reeves Young, LLC's Fee
and Insurance.
Attachments:
CHANGE EVENT LINE ITEMS
Revenue Cost Budget
Budget Code Vendor / Contract UOM QTYUnit Cost ROMPrime PCO Latest
Price QTYUnit Cost ROM RFQCommit. Latest
Cost
Over/
Under QtyUnit Cost ROM
26-0000- -.SUB J & I Cordon Electric, LLCls 1.0 $9,569.25$9,569.25 $9,569.25 1.0 $9,569.25$9,569.25 $9,569.25 1.0 $9,569.25$9,569.25
Reeves Young Page 1 of 2 Printed on: 7/15/2026 at 02:02PM EDT