GovernSmyrna.

25122--Tolleson-Park-Aquatics-Center-002-PCCO-#002-July-2026_CroySigned

Open official source ↗ · Source page 59

SHA-256 c31c4bee4f5ca172e0868b403f9bd2686b51a3f87b36bd2bec0f2ad0838008cc · Captured source extract

Reeves Young
45 Peachtree Industrial Blvd
Sugar Hill, Georgia 30518
P: (770) 271-1159
Project: 25122- - Tolleson Park Aquatics Center
3530 King Springs Rd
Smyrna, Georgia 30080
CHANGE EVENT #051 - Power for Portable Restrooms
Origin:
Date Created: 7/15/2026 Created By: Semmes Irby
Status: Open Scope: TBD
Type: Cost of Work Change Reason: Cost of Work
Description: This Change Event #051 is created to capture costs of electrical work required to bring power to Portable Restroom at T ennis Courts. This Work is outside of the current scope
of the Work and constitutes a change. CE is comprised of costs for time/labor, material, and equipment needed to install 750' of SO cord from site panel to Portable Restroom
(provided by City), as well as all other components required for a complete installation. CE originates from multiple conversations with CROY/City in OAC Meetings, in which it
was determined that while Restroom Building is under construction, City was to provide Portable Restrooms available for use to residents at the T ennis Court area. RY was to
bring power to T emporary Restrooms and ensure operation of the facility. This change is necessary in order to make T emporary Restroom Facility functional.
 
Contract Documents:
1. Amended to incorporate the Work modifications identified above. 
 
The Work:
1. As described above.
   
Contract Time: 
1. N/A
 
Contract Sum: 
1. Per breakdown below. 
 
Reeves Young, LLC reserves its' right to an equitable adjustment to the schedule and General Conditions required for the schedule impacts related to the scope of work
identified in this change order, but not known at this time until final commitments of fabrication and delivery are committed by Subcontractor(s). Should additional funds and time
be required to complete the project, Reeves Young reserves our right to increase our General Conditions, General Requirements, Fee, Overhead, Bond, and Insurance costs
for the additional funds required to complete the project. Reeves Young, LLC and the City of Smyrna ("Owner") agree to work together with due diligence to determine the
adjustment due Reeves Young. By executing this Change Event, Ownership agrees that additional cost shall be Submitted by Reeves Young, LLC in a future Owner Change
Order and/or Invoice to Owner. Owner agrees to Pay Reeves Young, LLC the total amount of the Owner Change Order and/or Invoice which includes Reeves Young, LLC's Fee
and Insurance.
Attachments:
 
CHANGE EVENT LINE ITEMS
Reeves Young Page 1 of 2 Printed on: 7/15/2026 at 02:07PM EDT