May 01, 2025 
6:00 PM 
 
City of Smyrna 
Mayor and Council Meeting 
2800 King Street SE 
Human Resources Training Room 
 
Page 6 of 8 
 
 A. COW2025-055 Discussion regarding Windy Hill Paving request from Baldwin – Eric Randall 
 
Eric Randall, Public Works Director, explained that Baldwin Paving has asked permission 
to pave overnight. They sent a letter with a description of their plan, and it is as follows: 
  
Baldwin Paving would like to explain the sequencing of the paving operation when we 
place topping on the mainline as well as both the WB and EB local access lanes. See 
below.  
• Paving the mainline and local access roads and side streets will all take place a 
night until finished. 
•  Baldwin will have traffic cops blocking the sections of road as we are paving on 
the local access roads. 
• Baldwin plans to pave the mainline lanes starting the night of May 8th, 2025. We 
will start with EB side starting just past Old Concord Rd toward South Cobb Drive 
intersection, skip the intersection and continue moving toward to Atlanta Road and 
flip and go WB from Atlanta Road back toward South Cobb Drive to Old Concord 
Rd. We will pave throughout the week until finished. We expect 4-5 nights to pave 
this portion. 
• Local Access - Will start on WB from Atlanta Rd moving toward South Cobb Drive 
then loop around and pave EB from South Cobb Drive toward Atlanta Rd 
• The first section will be WB from Atlanta Rd to Bridge #2; we will pave 15’ft wide 
pulls from the barrier wall 
• The second section will be WB from Bridge #2 to Bridge #1; we will pave 15’ft wide 
pulls from the barrier wall 
• The third section will be WB from Bridge #1 to South Cobb Drive; we will pave 15’ft 
wide pulls from the barrier wall 
• We will come back and start WB from Atlanta Rd to Bridge #2 and pave the 
remaining 4’ft and any side streets and continue the section sequence from Bridge 
#2 to Bridge #1 and then from Bridge #1 to South Cobb Drive. 
• We estimate that each local access road will take 3 nights to pave. 
• When we start on the EB side, we will pave 15’ft wide pulls like the WB side from 
South Cobb Drive to Bridge #1, then from Bridge #1 to Bridge #2, and last Bridge 
#2 to Atlanta Road. 
• Once the 15’ft pulls are complete, we will pave the remaining 4’ft pulls with the 
same sequence starting back from South Cobb Dr. to Bridge #1 and so forth. 
• Baldwin will have our striping sub onsite to stripe temp on final as the pave 
operation goes along 
 
Discussion took place regarding the timing of these road closures because it is graduation 
season and Mother’s Day weekend. This item will be added to the Consent Agenda.  
 
Mayor Norton discussed issues with Cobb County and the City of Mableton. Discussion took 
place about the street closures for the Market Village area. A reasonable compromise came 
forward that allowed for exit and entrance at the major openings and only closing the middle 
portions. This would only be during the times King Street is closed for safe access to the 
greenspace. The road closure item will be added to the Consent Agenda until an alternative 
comes forward so they are prepared for the Sundays to come. Mayor Norton also mentioned that 
the American Idol / Hometown Hero group contact the city to celebrate a local contestant. More 
information will come later.  
  
Richard Garland, Community Services Administrator, updated the Mayor and Council on the 
following projects: