Richard Garland, Community Services Administrator, provided the following updates 
  
Creatwood Park 
Next Steps:  
Complete Final Checklist 
Open Park: Monday, June 16th 
Ribbon Cutting: Friday, June 27th  
  
River Line Park Splashpad 
Infrastructure is being installed, removal of old concrete slabs, installation of sewer line 
Next Steps: 
Layout building 
Foundations 
Plumbing 
  
Anticipated Completion: 
Rain is impacting schedule with an anticipated completion date of December 2025 
  
Village Green Bathroom & Playground 
Next Steps: 
Playground equipment footer install 
Shade structure foundation install 
Building vertical 
  
Anticipated Completion: 
Behind schedule with an anticipated completion date of August 2025 
  
Tolleson Park Aquatics 
Next Steps: 
Complete Demo 
Grade out to pad ready site 
Design Work ongoing, schematic designs submitted this past week for staff review 
  
Anticipated Completion: 
April 2027 
  
Sports Lighting Conversion 
Next Steps: 
Completing Jonquil Park 
  
Anticipated Completion: 
July 2027 
  
Other Projects: 
Tolleson Park Bridge Replacement (SPLOST):  
• Pre-bid meeting scheduled for June 17 
Rose Garden Park Pavilion and Playground (CDBG):  
• Foresite is completing final Construction Documents 
• Anticipated date to open project for bids is Fall of 2025 
Riverview Park Trail (TPL):  
• Formal agreement signed between City and TPL. Construction to begin this 
summer.