Issue Sheet ATH2025-077

Open official source ↗ · Source page 1

SHA-256 ff26d1ed47bbc3a4c05ed946a652a6d0b6d6c14f80c6d8d523ee9f73a1a21640 · Captured source extract

City of Smyrna
Issue Sheet
File Number: ATH2025-077
A Max Bacon
City Hall
2800 King Street
Smyrna, GA 30080 
1
0
7
8
Agenda Date: 5/5/2025
In Control: City Council File Type: Authorization
Agenda Section:
Formal Business
Department: Public Works
Agenda Title:
Authorization to approve change order / additional work for the Parkway Drive box culvert 
replacement project to K.M Davis Contacting Company, Inc. (3259 Austell Road, Marietta, GA 
30008) in an amount not to exceed $111,730.00 to be paid from the 2025 Stormwater fund 
and to bring the total project cost to a not to exceed amount of $496,570.00 and authorize 
the Mayor to sign and execute all documents.
Ward 5 Councilmember - Susan Wilkinson
ISSUE AND BACKGROUND:
This request is based off an already approved stormwater project by mayor and council that 
was approved on 8.26.24. In an amount not to exceed $384,840.00. However, due to 
unforeseen utility issues with Atlanta Gas Light we were required to meet certain depth / 
coverage requirements by them which required the city to expand our scope slightly to 
achieve those requirements. In return caused need for a change order in an amount not to 
exceed $111,730.00 to be funded from 2025 stormwater.
RECOMMENDATION / REQUESTED ACTION:
Public Works reommends approval of a change order / additional work for the Parkway Drive box 
culvert replacement project to K.M Davis Contacting Company, Inc. (3259 Austell Road, Marietta, GA 
30008) in an amount not to exceed $111,730.00 to be paid from the 2025 Stormwater fund and to 
bring the total project cost to a not to exceed amount of $496,570.00 and authorize the Mayor to sign 
and execute all documents.