 Splashpad / Sprayground  
• Scope: Construction of a Splashpad at River Line Park to expand the offerings of 
the park. 
• Status: Council approved the award of the project to Integrated Construction & 
Nobility (ICAN) on February 3rd, 2025; Staff has held a project kick-off meeting 
with ICAN 
 
 Sidewalks/Trails/Greenways/Beautification  
• 30% Of proposed budget spent to Date 
• Additional 5% Estimated to be spent on:  
- Decorative Tree Fencing in Market Village – 100% Complete  
- Phase 2 Landscaping – Fire Station 1-5, Police Station and Back Side of 
Library/City Hall, Park Area at West Spring Street Intersection across from 
Moe’s near the Railroad Tracks – 90% Complete 
- Up lighting around Trees – Market Village and City Hall - Complete 
 
Upcoming Projects 
Cobb Parkway Pedestrian Bridge to the Battery  
• Status: Projected 2026 – County has begun concept development. 
• Project has received Community Project Funding of $1,000,000; ARC TIP Project 
No. CO-496 
 
Camp Highland – Complete Bridge Replacement  
• Status: Staff has worked with Cobb DOT to nail down the restorative scope 
following initial bid. 
• Council voted to increase the project budget by $94,200.00 on February 17, 2025 
to meet the cost share agreement with the County. 
• Current Budget: $1,594,200 
 
Additional Projects 
• Facility Improvements  
- Status: 72% of Budget Obligated  
• Environmental Improvements  
- Status: 100% of Budget Obligated for GA Power Contract  
• Curb and Gutter  
- Status: 4% of Budget Obligated  
• Sidewalks/Trails/Greenways /Beautification  
- Status: 29% of Budget Obligated  
• Traffic Calming  
- Status: 36% of Budget Obligated  
• Public Safety – 800 MHz Radio Replacement  
- Status: 82% of Budget Obligated  
• Fire Department – Small Equipment  
- Status: 100% of Budget Obligated 
  
 Joint Projects with County 
 East West Connector Roadway Safety Improvements  
• Status: The County’s design is continuing into the next stages. 
• Based on the EW Connector Needs Assessment that was completed by Cobb 
DOT in 2024, improvements to the intersections at Fontaine Road and at Cooper 
Lake Road have been identified. 