Capital Improvement Plan 
FY 2024 to FY 2028 
The Capital Improvement Plan (CIP) is a document approved by Mayor & Council along with the 
Operating Budget to outline a 5-year plan for upgrading, maintaining, and replacing the City’s 
capital assets. Capital assets cost at least $20,000 and have a useful life of at least three years.  
The “CIP” encompasses four capital project funds: General Fund CIP, E-911 CIP, Water/Sewer CIP, 
and Storm Water CIP. The General Fund CIP and the E-911 CIP are normally funded by transfers-in 
from the General Fund. In FY24, $1,483,000 of current projects will be funded by the American 
Rescue Plan Act (ARPA) Fund. The remaining $800,000 will be funded by a transfer-in from the 
General Fund. The Water/Sewer CIP is funded by a transfer-in from the Water/Sewer Fund. The 
Storm Water CIP is funded by a storm water fee assessed on residential and commercial properties.  
Departments submitted their new and revised capital requests for review by the CIP Committee, an 
ad-hoc committee composed of staff from Administration, Finance, and select departments. 
 
General Fund CIP 
The Committee recommends 41 projects for the FY 2024 - FY 2028 CIP.  Twenty-nine of these 
projects are carried over from the FY 2023 - FY 2027 CIP adopted by Mayor & Council in the FY 
2023 budget process. Twelve projects are new requests from the Departments: 
• 3 new requests to fund Parks project 
• 5 new requests to fund Public Safety projects 
• 4 new requests to fund Public Works projects  
 
 
 
 
 
 
 
 
 