Projects Eliminated or Moved Out of FY 2024
Below is a summary of the projects requested by departments for funding in FY 2024 that the CIP
Committee eliminated or delayed to a future year:
General Fund CIP
iPlan Tables Fire $20,040
Removed from CIP schedule. Recommended to request through operating budget.
Public Access Defibrillator Program Fire $80,000
Pushed one year.
Outside Covering and Asphalt Flooring Hwys & Streets $77,000
Pushed one year.
Material Shed Storage Hwys & Streets $80,000
Pushed one year.
Street Striping Hwys & Streets $20,000
Removed funds for FY24 and recommended funding from 2022 SPLOST.
Security Camera/Access Control System IT $650,000
Pushed one year. Recommended to explore alternate funding source.
Technical Services Renovation Library $60,000
Pushed one year.
Wolfe Center Renovations Parks Programs $100,000
Removed from CIP schedule. Recommended to fund from previous CIP project and operating budget.
Parks Equipment Parks Maintenance $50,000
Removed FY 2024 request. Recommended potential funding from operating budget.
Bathroom and Storage Building Parks Maintenance $500,000
Removed from CIP schedule. Recommended use of alternate funding source.
Wedding Gazebo & Grounds Upgrades Parks Maintenance $100,000
Pushed start of project back one year.
Sports Field Fencing, Windscreens, Netting Parks Maintenance $20,000
Removed FY 2024 funding and recommended requesting through operating budget.
Video Management System Police $294,000
Pushed one year. Recommended to explore alternate funding source.
General Fund CIP Projects Eliminated or Moved Out of FY 2024 $2,051,040