Capital Improvement Plan
FY 2026 to FY 2030
The Capital Improvement Plan (CIP) is a document approved by Mayor & Council along with the
Operating Budget to outline a 5-year plan for upgrading, maintaining, and replacing the City’s
capital assets. Capital assets cost at least $20,000 and have a useful life of at least three years.
The “CIP” encompasses four capital project funds: General Fund CIP, E-911 CIP, Water/Sewer CIP,
and Storm Water CIP. The General Fund CIP and the E-911 CIP are funded by transfers-in from the
General Fund. The Water/Sewer CIP is funded by a transfer-in from the Water/Sewer Fund. The
Storm Water CIP is funded by a storm water fee assessed on residential and commercial properties.
Departments submitted their new and revised capital requests for review by the CIP Committee, an
ad-hoc committee composed of staff from Administration, Finance, and select departments.
General Fund CIP
The Committee recommends 57 projects for the FY 2026 - FY 2030 CIP. 40 of these projects are
carried over from the FY 2025 - FY 2029 CIP adopted by Mayor & Council in the FY 2025 budget
process. 17 projects are new requests from the Departments:
• 4 new requests to fund IT projects
• 2 new requests to fund Library projects
• 1 new request to fund a Parks project
• 1 new request to fund a Fire project
• 3 new requests to fund Police projects
• 6 new requests to fund Public Works projects